HomeHSA Site Safety Exam PrepQuestions 21–30
HSA Site Safety Exam PrepPart 3 of 3

HSA Site Safety Exam Prep Exam Questions & Answers 2026 (21–30)

HSA Site Safety Exam Prep practice questions and answers 2026. Tap an option to test yourself — you'll see the correct answer and a plain-English explanation for every question. Free, no login.

Practise HSA Site Safety Exam Prep questions free, download the PDF, or unlock timed mock exams when you are ready.
Multiple choice — pick the best answer, then reveal it
  1. Q21During a pre-use check, a dumper's reversing alarm is found to be faulty, but a vehicle marshal is available. What is the correct action?

    • AOperate the vehicle only in forward gears for the shift
    • BReport the defect at the end of the working shift
    • CProceed with caution using the mirrors and horn
    • DDo not use the dumper until repaired
    • EUse the dumper since a vehicle marshal is present
    Show answer

    ✓ Correct answer: D. Do not use the dumper until repaired

    Isolate the dumper immediately. Safety devices like reversing alarms must be functional; a marshal is an additional control, not a substitute for defective equipment.

  2. Q22Under LOLER, when is a new lifting accessory exempt from a thorough examination before its first use on a site?

    • AWith a Declaration of Conformity under 1 year old
    • BWhen it has been manufactured within the last two years
    • CIf the site manager completes a visual inspection log
    • DWhen it is hired from a certified equipment provider
    • EIf it is strictly used for lifting light loads only
    Show answer

    ✓ Correct answer: A. With a Declaration of Conformity under 1 year old

    A Declaration of Conformity issued within the last 12 months exempts new equipment from immediate thorough examination, as it certifies manufacturing safety compliance.

  3. Q23What is the most effective immediate control measure to minimize silica dust exposure when cutting concrete kerbs?

    • ASweep the dust immediately after use
    • BStand upwind while cutting the kerb
    • CUse on-tool water suppression
    • DWear a standard disposable face mask
    • ERotate the task between two workers
    Show answer

    ✓ Correct answer: C. Use on-tool water suppression

    Wet cutting suppresses dust at the source. This engineering control is significantly more effective than PPE or administrative measures in preventing airborne silica exposure.

  4. Q24A mobile plant vehicle must reverse in a confined area with pedestrians. What is the most effective safety measure?

    • ARely on the reversing alarm and horn
    • BInstall convex mirrors on site fence
    • CInstruct the driver to check mirrors
    • DEnsure pedestrians wear hi-vis vests
    • EUse barriers and a vehicle marshal
    Show answer

    ✓ Correct answer: E. Use barriers and a vehicle marshal

    Physical segregation combined with a vehicle marshal is most effective. This prevents pedestrians entering the danger zone, unlike mirrors or alarms which have limitations.

  5. Q25An operative discovers a cut in an electrical cable exposing the inner wires. What is the immediate action?

    • AContinue using if the tool works
    • BStop use and remove the cable
    • CTape over the cut with electrical tape
    • DAvoid touching the damaged section
    • EReport it at the end of the shift
    Show answer

    ✓ Correct answer: B. Stop use and remove the cable

    Immediately remove the cable from service. Taping is not a safe repair; only a competent person can properly restore insulation integrity and mechanical strength.

  6. Q26Who is legally responsible for carrying out the daily pre-use check on a piece of plant before the shift begins?

    • AThe hire company agent
    • BThe construction client
    • CThe maintenance fitter
    • DThe plant operator
    • EThe site safety manager
    Show answer

    ✓ Correct answer: D. The plant operator

    The operator is responsible for checking their equipment before use to ensure it is safe for the shift.

  7. Q27When an excavator is used to lift suspended loads, what specific documentation is required under LOLER?

    • AThorough examination report
    • BManufacturer's warranty document
    • CStandard roadworthiness certificate
    • DOperator's daily inspection logbook
    • EHeavy goods vehicle license card
    Show answer

    ✓ Correct answer: A. Thorough examination report

    Using an excavator for lifting duties classifies it as lifting equipment under LOLER, requiring a Report of Thorough Examination.

  8. Q28Which position presents the highest risk of crushing for a vehicle marshal guiding a reversing truck?

    • AOn a raised observation platform
    • BAt the side of the site entrance
    • CBetween the truck and a wall
    • DStanding on the pedestrian walkway
    • EVisible in the driver's mirror
    Show answer

    ✓ Correct answer: C. Between the truck and a wall

    Standing between a vehicle and a fixed structure creates a crushing zone with no escape route for the marshal.

  9. Q29A safety-critical fault on a tool has been repaired. What must be done before it is used again?

    • AWait 24 hours for cool down
    • BObtain a manufacturer waiver
    • CUse immediately to test it
    • DLog the repair in the diary
    • ECarry out a pre-use check
    Show answer

    ✓ Correct answer: E. Carry out a pre-use check

    Operators must perform a pre-use check to verify the tool is safe and ready for use after any repairs.

  10. Q30What is the primary factor when selecting hearing protection for using a breaker?

    • AThe weight of the ear muffs
    • BThe specific noise level
    • CThe brand of ear defenders
    • DThe high visibility color
    • EThe cost of the protection
    Show answer

    ✓ Correct answer: B. The specific noise level

    Hearing protection must be matched to the noise level to provide adequate attenuation without over-protecting.

Free practice here. Timed mocks when you are ready.

Use the free HSA Site Safety Exam Prep sample, download the PDF, then unlock web-based timed mock exams for a full exam rehearsal.