  1. Q21What is the minimum safe working distance for mobile plant operating near overhead power lines rated at 33 kV?

    • A15 metres
    • B3 metres
    • C9 metres
    • D6 metres
    Show answer

    ✓ Correct answer: D. 6 metres

    For overhead power lines rated between 33 kV and 66 kV, the minimum safe working distance is 6 metres to prevent arcing and electrocution risks.

  2. Q22Before excavation work begins, what is the PRIMARY purpose of using a Cable Avoidance Tool (CAT) and Signal Generator (Genny)?

    • ATo test soil contamination levels
    • BTo measure soil compaction
    • CTo locate underground services
    • DTo determine the water table depth
    Show answer

    ✓ Correct answer: C. To locate underground services

    A CAT and Genny are used together to locate and trace underground services such as electric cables, gas pipes, and telecommunications lines before digging to prevent strikes.

  3. Q23Under what circumstances can an excavator be used as a lifting appliance on a construction site?

    • AWhenever the site supervisor gives permission
    • BWhen it has been designed, tested and certified for lifting by the manufacturer
    • COnly for loads under 500 kg
    • DWhen no other lifting equipment is available
    Show answer

    ✓ Correct answer: B. When it has been designed, tested and certified for lifting by the manufacturer

    Excavators can only be used for lifting if they have been specifically designed and tested for that purpose by the manufacturer, with appropriate certification and marked safe working loads.

  4. Q24What document must be in place before entering a confined space on a construction site?

    • AA permit-to-work
    • BA toolbox talk register
    • CA COSHH assessment only
    • DA delivery note
    Show answer

    ✓ Correct answer: A. A permit-to-work

    A permit-to-work system is mandatory for confined space entry. It ensures all risks have been assessed, controls are in place, and authorized persons approve the work before entry.

  5. Q25What is the minimum depth of excavation at which edge protection or barriers must be provided to prevent falls?

    • A5 metres
    • B1 metre
    • C3 metres
    • D2 metres
    Show answer

    ✓ Correct answer: D. 2 metres

    Edge protection must be provided for excavations 2 metres or deeper to prevent workers from falling in. Shallower excavations may also require protection depending on risk assessment.

  6. Q26Who must be appointed in writing to supervise lifting operations involving a tower crane on site?

    • AThe crane operator
    • BAny site supervisor
    • CAn appointed person
    • DThe health and safety officer
    Show answer

    ✓ Correct answer: C. An appointed person

    Under the Lifting Operations and Lifting Equipment Regulations (LOLER), an appointed person must be designated in writing to plan and supervise all lifting operations.

  7. Q27What colour are underground gas pipes typically painted or marked in the UK utility colour code?

    • ARed
    • BYellow
    • CBlue
    • DGreen
    Show answer

    ✓ Correct answer: B. Yellow

    According to UK utility marking standards, gas pipes are identified with yellow markings to distinguish them from other underground services.

  8. Q28Before a lift is made using a mobile crane, what calculation must be checked to ensure safety?

    • AThe radius and safe working load from the load chart
    • BThe fuel consumption rate
    • CThe crane's service history
    • DThe operator's hours worked that day
    Show answer

    ✓ Correct answer: A. The radius and safe working load from the load chart

    The radius and load chart must be checked to ensure the crane's safe working load is not exceeded at the specific operating radius and configuration.

  9. Q29In a confined space entry scenario, what is the PRIMARY role of the standby person positioned outside?

    • ATo prevent unauthorized access to the work area only
    • BTo pass tools and materials into the space
    • CTo record the time spent in the confined space
    • DTo maintain communication and raise the alarm if needed
    Show answer

    ✓ Correct answer: D. To maintain communication and raise the alarm if needed

    The standby person maintains constant communication with workers inside the confined space and can raise the alarm and initiate rescue procedures if an emergency occurs.

  10. Q30What is the purpose of a Temporary Works Coordinator (TWC) on a construction project?

    • ATo manage subcontractor payments
    • BTo order materials for the project
    • CTo ensure temporary structures are properly designed, checked and installed
    • DTo conduct final building inspections
    Show answer

    ✓ Correct answer: C. To ensure temporary structures are properly designed, checked and installed

    The TWC ensures that temporary structures such as scaffolding, propping, and excavation support are properly designed, checked, and safely installed before use.