HomePRINCE2 Agile FoundationQuestions 21–30
PRINCE2 Agile FoundationPart 3 of 3

PRINCE2 Agile Foundation Exam Questions & Answers 2026 (21–30)

PRINCE2 Agile Foundation practice questions and answers 2026. Tap an option to test yourself — you'll see the correct answer and a plain-English explanation for every question. Free, no login.

Practise PRINCE2 Agile Foundation questions free, download the PDF, or unlock timed mock exams when you are ready.
Download PDFWatch video
Multiple choice — pick the best answer, then reveal it
  1. Q21Which role carries direct responsibility for ensuring assigned products are produced to the required quality?

    • AProject Manager
    • BExecutive
    • CSenior User
    • DProject Board
    • ETeam Manager
    Show answer

    ✓ Correct answer: E. Team Manager

    The Team Manager is directly responsible for ensuring that the products assigned to their team are built to the required quality standard. Why the other options are incorrect: • Project Manager: The Project Manager oversees overall delivery but does not bear direct responsibility for producing individual products to quality. • Executive: The Executive focuses on business justification and does not manage product quality during delivery. • Senior User: The Senior User specifies quality expectations from a user perspective but does not develop the products. • Project Board: The Project Board provides governance and oversight but is not involved in hands-on product production.

  2. Q22Which of the following is NOT a purpose served by the Plans theme?

    • ARecording the benefits expected from the project
    • BDefining the contents of Work Packages
    • CEstablishing delivery schedules
    • DEstimating the resources required
    • EProviding a baseline for monitoring progress
    Show answer

    ✓ Correct answer: A. Recording the benefits expected from the project

    Recording expected benefits is a function of the Business Case theme; the Plans theme does not capture benefit information. Why the other options are incorrect: • Defining the contents of Work Packages: Defining Work Packages is a core output of the Plans theme, carried out during stage planning. • Establishing delivery schedules: Establishing delivery schedules is a fundamental part of the planning process within this theme. • Estimating the resources required: Estimating the resources needed to deliver products is central to creating any plan. • Providing a baseline for monitoring progress: Approved plans serve as baselines against which actual progress is measured and reported.

  3. Q23Which document is used to keep the project board informed during Controlling a Stage?

    • AHighlight report
    • BProject brief
    • CClosure recommendation
    • DBenefits review plan
    • EDaily log
    Show answer

    ✓ Correct answer: A. Highlight report

    Highlight reports are issued regularly during Controlling a Stage to update the project board on progress while minimising the need for daily board involvement. Why the other options are incorrect: • Project brief: The project brief is created during Starting Up a Project and has no role in stage-level reporting. • Closure recommendation: A closure recommendation is produced at the end of the project, not during stage control. • Benefits review plan: The benefits review plan is developed during project initiation and is not a stage-control document. • Daily log: The daily log is a personal record maintained by the project manager and is not a formal board update.

  4. Q24Who is responsible for capturing lessons learned during the delivery of a work package?

    • ATeam manager
    • BProject manager
    • CExecutive
    • DSenior supplier
    • EProject support
    Show answer

    ✓ Correct answer: A. Team manager

    The team manager identifies and records lessons arising from the delivery of their work package. Why the other options are incorrect: • Project manager: The project manager compiles lessons at the project level rather than at the work package level. • Executive: The executive does not play a role in identifying delivery lessons. • Senior supplier: The senior supplier may contribute input but does not lead the lessons-learned process. • Project support: Project support may record lessons but does not identify them.

  5. Q25In PRINCE2, what role does a checkpoint report serve?

    • ATo provide ongoing justification for investing in the project
    • BTo keep the project manager informed about how the team is progressing
    • CTo establish what the project is intended to deliver and achieve
    • DTo give senior corporate management confidence that the project is on track
    • ETo assign packages of work to the relevant teams
    Show answer

    ✓ Correct answer: B. To keep the project manager informed about how the team is progressing

    The checkpoint report exists to keep the project manager informed of progress at team level during a stage. Why the other options are incorrect: • To provide ongoing justification for investing in the project: Justifying continued investment is the purpose of the business case, not the checkpoint report. • To establish what the project is intended to deliver and achieve: Project scope and objectives are established in the project brief, not in checkpoint reports. • To give senior corporate management confidence that the project is on track: Providing assurance to senior management is achieved through highlight reports, not checkpoint reports. • To assign packages of work to the relevant teams: Work is allocated to teams through work package authorisation, which is separate from checkpoint reports.

  6. Q26Which combination of activities correctly underpins business justification?

    • AContinuous benefit analysis AND regular risk assessment
    • BConcentrating solely on costs AND disregarding benefits
    • CKeeping suppliers satisfied AND completing the project on time
    • DHigh team morale AND the chosen management approach
    • EA rigid plan AND an unwillingness to adapt
    Show answer

    ✓ Correct answer: A. Continuous benefit analysis AND regular risk assessment

    Maintaining business justification depends on continuously analysing benefits and understanding the associated risks. Why the other options are incorrect: • Concentrating solely on costs AND disregarding benefits: Disregarding benefits removes the very foundation of business justification. • Keeping suppliers satisfied AND completing the project on time: How satisfied suppliers are has no bearing on whether the project remains justified. • High team morale AND the chosen management approach: Team morale and management style are not indicators of whether business justification holds. • A rigid plan AND an unwillingness to adapt: A rigid plan that cannot respond to change can actively damage business justification.

  7. Q27What is the primary intention of the PRINCE2 principle 'Manage by exception'?

    • ADefine agreed tolerances so that authority can be safely delegated
    • BEliminate the requirement for project planning
    • CEnsure that no risks arise during the project
    • DDiminish the influence of the Project Board
    • EPrevent any reporting obligations to stakeholders
    Show answer

    ✓ Correct answer: A. Define agreed tolerances so that authority can be safely delegated

    The principle defines acceptable limits across time, cost, quality, scope, risk and benefits, enabling delegation of authority without the need for constant oversight. Why the other options are incorrect: • Eliminate the requirement for project planning: Planning remains essential; tolerance thresholds are derived from the project plan. • Ensure that no risks arise during the project: Risks do not disappear; they continue to be identified and managed within tolerances. • Diminish the influence of the Project Board: The Project Board retains its key role, particularly when tolerance limits are forecast to be breached. • Prevent any reporting obligations to stakeholders: Reporting to stakeholders continues; the exception principle does not remove that obligation.

  8. Q28Which two statements accurately describe the Project Board?

    • AIt represents business, user AND supplier interests AND provides governance
    • BIt manages day-to-day project tasks AND oversees team activities
    • CIt removes all project risks AND resolves all issues
    • DIt maintains the lessons log AND tracks benefit realisation
    • EIt sets quality criteria AND defines product scope
    Show answer

    ✓ Correct answer: A. It represents business, user AND supplier interests AND provides governance

    The Project Board fulfils a governance role that brings together business, user and supplier perspectives to direct and authorise the project. Why the other options are incorrect: • It manages day-to-day project tasks AND oversees team activities: Day-to-day management is the responsibility of the Project Manager, not the Project Board. • It removes all project risks AND resolves all issues: Risks and issues are managed rather than eliminated, and this responsibility is broader than the Project Board alone. • It maintains the lessons log AND tracks benefit realisation: Maintaining lessons and tracking benefits are activities carried out through other mechanisms, not directly by the Project Board. • It sets quality criteria AND defines product scope: Quality criteria and product scope are defined through the Quality and Plans themes, not by the Project Board.

  9. Q29Why does PRINCE2 include tailoring as a key concept?

    • ATo fit the method appropriately to the project's unique context
    • BTo strip out all governance steps from the process
    • CTo make every project follow an identical approach
    • DTo remove quality management from the project lifecycle
    • ETo disregard the needs and expectations of stakeholders
    Show answer

    ✓ Correct answer: A. To fit the method appropriately to the project's unique context

    Tailoring allows PRINCE2 to be applied in a way that is proportionate to the project's environment, scale, complexity, and level of risk. Why the other options are incorrect: • To strip out all governance steps from the process: Governance is a fundamental requirement and is never removed, even when the method is tailored to fit the project. • To make every project follow an identical approach: Tailoring embraces the differences between projects; it does not impose a uniform or identical approach. • To remove quality management from the project lifecycle: Quality management remains a core activity regardless of how the method is tailored for a given project. • To disregard the needs and expectations of stakeholders: Stakeholder needs are always considered and remain central to any tailored application of PRINCE2.

  10. Q30Which of the following is NOT an advantage of developing a PID?

    • AServes as the definitive reference document for the project
    • BEstablishes governance and control arrangements
    • COutlines the day-to-day duties of the project board
    • DDefines the baseline plans and management strategies
    • ERecords the detailed justification for the project
    Show answer

    ✓ Correct answer: C. Outlines the day-to-day duties of the project board

    The PID does not outline the daily duties of the project board — this is not one of its purposes. Why the other options are incorrect: • Serves as the definitive reference document for the project: Acting as the primary reference point is a recognised purpose of the PID. • Establishes governance and control arrangements: Establishing governance and control arrangements is a core PID function. • Defines the baseline plans and management strategies: Setting baseline plans and strategies is a key benefit of the PID. • Records the detailed justification for the project: Capturing the detailed project justification is a central PID purpose.