HomePVDS Test PrepQuestions 11–20
PVDS Test PrepPart 2 of 3

PVDS Test Prep Exam Questions & Answers 2026 (11–20)

PVDS Test Prep practice questions and answers 2026. Tap an option to test yourself — you'll see the correct answer and a plain-English explanation for every question. Free, no login.

Practise PVDS Test Prep questions free, download the PDF, or unlock timed mock exams when you are ready.
Multiple choice — pick the best answer, then reveal it
  1. Q11According to most electric service providers, which of the following is typically required before a PV system can be interconnected to the grid?

    • AMarketing plan approval
    • BSigned interconnection agreement
    • CSocial media promotion
    • DCustomer credit score check
    Show answer

    ✓ Correct answer: B. Signed interconnection agreement

    An interconnection agreement is a legal contract between the customer and the utility that must be executed before a PV system can be connected to the grid, outlining terms, conditions, and responsibilities.

  2. Q12When reviewing the construction plan set for a new commercial building with planned PV, which drawing would contain information about the existing electrical service capacity?

    • AElectrical site plan
    • BLandscaping blueprint
    • CInterior design layout
    • DMarketing floor plan
    Show answer

    ✓ Correct answer: A. Electrical site plan

    Electrical site plans typically show the existing electrical service capacity, including service entrance, main panel location, and capacity information that is critical for PV integration planning.

  3. Q13Which type of document would specify the wind and snow load ratings that a roof-mounted PV system must be designed to withstand?

    • AMarketing agreement
    • BUtility bill format
    • CEquipment color chart
    • DStructural engineering specifications
    Show answer

    ✓ Correct answer: D. Structural engineering specifications

    Structural engineering specifications detail the required wind and snow load ratings that any rooftop equipment, including PV systems, must be designed to withstand based on local conditions and building codes.

  4. Q14According to the 2017 NEC, what is required for PV systems on buildings with rapid shutdown?

    • ACellular communication backup
    • BRedundant power supplies
    • CConductors limited to no more than 30 volts within 30 seconds
    • DManual reset capability only
    Show answer

    ✓ Correct answer: C. Conductors limited to no more than 30 volts within 30 seconds

    NEC 690.12 requires that conductors be limited to no more than 30 volts within 30 seconds of rapid shutdown initiation, providing safety for first responders in emergency situations.

  5. Q15When reviewing project criteria for a proposed PV system, which document would contain the requirements for fire department access pathways on the roof?

    • AEquipment warranty
    • BLocal fire code
    • CUtility rate schedule
    • DMarketing guidelines
    Show answer

    ✓ Correct answer: B. Local fire code

    Local fire codes specify requirements for access pathways on roofs with PV systems to ensure firefighters have safe access routes for emergency operations.

  6. Q16Which of the following utility requirements would MOST directly affect the electrical configuration of a grid-tied PV system?

    • APower factor requirements
    • BBilling cycle timing
    • CCustomer service availability
    • DUtility company logo placement
    Show answer

    ✓ Correct answer: A. Power factor requirements

    Power factor requirements directly affect the electrical configuration of the system, as they dictate how the inverter must be programmed to deliver power at a specific power factor to maintain grid stability.

  7. Q17When reviewing covenants for a residential PV installation, which restriction would MOST impact the system's energy production capability?

    • AEquipment color requirements
    • BInstaller dress code
    • CBrand selection criteria
    • DRestrictions on module orientation
    Show answer

    ✓ Correct answer: D. Restrictions on module orientation

    Restrictions on module orientation can significantly impact energy production as they may prevent optimal positioning of panels to capture maximum sunlight, potentially reducing system output substantially.

  8. Q18According to the 2017 NEC, ground-mounted PV array fences must be at least how far from the array?

    • A60 inches
    • B12 inches
    • C36 inches
    • D24 inches
    Show answer

    ✓ Correct answer: C. 36 inches

    NEC 110.31 requires a minimum distance of 3 feet (36 inches) between ground-mounted PV arrays and fences to allow adequate working space for maintenance and service.

  9. Q19When reviewing electric service provider requirements, which of the following would typically be needed for systems larger than 10kW?

    • ASocial media announcement
    • BProfessional engineer's stamp on interconnection plans
    • CHomeowner's signature only
    • DMarketing approval
    Show answer

    ✓ Correct answer: B. Professional engineer's stamp on interconnection plans

    Systems larger than 10kW typically require a professional engineer's stamp on interconnection plans to verify that the system meets all utility and code requirements, ensuring safe and proper grid connection.

  10. Q20Which construction document would provide information about the existing electrical panel's bus bar rating?

    • AElectrical single-line diagram
    • BArchitectural elevation
    • CLandscape plan
    • DMarketing floor plan
    Show answer

    ✓ Correct answer: A. Electrical single-line diagram

    Electrical single-line diagrams show the electrical distribution system including panel bus bar ratings, which are critical for determining available capacity for PV interconnection.