  1. Q21'System scaffolding' (modular scaffold) differs from tube and coupler scaffolding because:

    • AIt cannot be used above 4 metres
    • BIt does not require a licence to erect
    • CIt uses pre-engineered components with predetermined connection points, offering faster erection and consistent geometry
    • DIt is only suitable for internal use
    Show answer

    ✓ Correct answer: C. It uses pre-engineered components with predetermined connection points, offering faster erection and consistent geometry

    Topic: Components And Types

  2. Q22Which component prevents a scaffold from swaying in the plane parallel to the building face?

    • ATransoms
    • BLongitudinal (facade) bracing
    • CBase plates
    • DToe boards
    Show answer

    ✓ Correct answer: B. Longitudinal (facade) bracing

    Topic: Components And Types

  3. Q23What is the function of 'plan bracing' in scaffolding?

    • ATo support loads from above
    • BTo carry out the handover inspection
    • CTo anchor the scaffold to the building
    • DTo resist horizontal forces in the plan (horizontal) plane, preventing racking at each lift level
    Show answer

    ✓ Correct answer: D. To resist horizontal forces in the plan (horizontal) plane, preventing racking at each lift level

    Topic: Components And Types

  4. Q24A 'coupler' (clamp) used in tube and coupler scaffolding must be:

    • ACompliant with AS 1576 and free from visible defects such as cracks, distortion, or damaged threads
    • BColour-coded by the hire company
    • CMade only of aluminium
    • DTightened by hand — not with a spanner
    Show answer

    ✓ Correct answer: A. Compliant with AS 1576 and free from visible defects such as cracks, distortion, or damaged threads

    Topic: Components And Types

  5. Q25What is a 'swivel coupler' used for?

    • AConnecting two tubes at 90°
    • BConnecting the standard to the base plate
    • CConnecting two tubes at any angle for bracing
    • DLifting tube sections into position
    Show answer

    ✓ Correct answer: C. Connecting two tubes at any angle for bracing

    Topic: Components And Types

  6. Q26A 'right-angle coupler' (also called a load-bearing coupler) is used:

    • AOnly for diagonal braces
    • BTo connect ledgers and transoms to standards at 90°, and transfers load through the coupler
    • COnly on external scaffolds
    • DTo join two tubes end-to-end
    Show answer

    ✓ Correct answer: B. To connect ledgers and transoms to standards at 90°, and transfers load through the coupler

    Topic: Components And Types

  7. Q27Scaffold boards must comply with:

    • AThe site manager's preference
    • BAS 2082 (structural timber)
    • CNo specific standard — any timber can be used
    • DAS 1577 (scaffold planks) or be steel/aluminium decking rated for the required load
    Show answer

    ✓ Correct answer: D. AS 1577 (scaffold planks) or be steel/aluminium decking rated for the required load

    Topic: Components And Types

  8. Q28The maximum overhang of a scaffold board beyond its support (transom) is:

    • A4 times the board thickness (typically up to about 150 mm for a 38 mm board)
    • B1 metre
    • C500 mm regardless of thickness
    • DNo limit if the board is tied
    Show answer

    ✓ Correct answer: A. 4 times the board thickness (typically up to about 150 mm for a 38 mm board)

    Topic: Components And Types

  9. Q29What is a 'spigot' used for in system scaffolding?

    • AConnecting bracing diagonals
    • BAligning base plates
    • CJoining two standard tubes end-to-end (top-to-bottom connection)
    • DAttaching the guardrail post
    Show answer

    ✓ Correct answer: C. Joining two standard tubes end-to-end (top-to-bottom connection)

    Topic: Components And Types

  10. Q30Aluminium scaffold components must not be used:

    • AAbove 10 metres
    • BIn environments where they contact substances that attack aluminium (e.g. strong alkalis in wet cement)
    • COn any construction site
    • DIn windy conditions
    Show answer

    ✓ Correct answer: B. In environments where they contact substances that attack aluminium (e.g. strong alkalis in wet cement)

    Topic: Components And Types