HomeSMSTS Exam Prep 2026Questions 21–30
SMSTSPart 3 of 3

SMSTS Exam Questions & Answers 2026 (21–30)

SMSTS practice questions and answers 2026. Tap an option to test yourself — you'll see the correct answer and a plain-English explanation for every question. Free, no login.

Practise SMSTS questions free, download the PDF, or unlock timed mock exams when you are ready.
Download PDFWatch video
Multiple choice — pick the best answer, then reveal it
  1. Q21You notice repeated minor breaches of site rules by a subcontractor. What approach best reflects the purpose of health and safety law?

    • AAddress the behaviour promptly and reinforce standards before a serious incident occurs
    • BIgnore minor breaches until a serious issue arises
    • CImmediately remove the subcontractor from site
    • DIssue written warnings only after an accident
    • ELeave enforcement solely to the subcontractor’s supervisor
    Show answer

    ✓ Correct answer: A. Address the behaviour promptly and reinforce standards before a serious incident occurs

    Health and safety law promotes proactive risk management. Early intervention helps prevent escalation and demonstrates effective control of the workplace. Why the other options are incorrect: • Ignore minor breaches until a serious issue arises: Waiting allows unsafe behaviours to become normalised. • Immediately remove the subcontractor from site: Immediate removal may be disproportionate without investigation. • Issue written warnings only after an accident: Post-incident action defeats the preventative purpose of the law. • Leave enforcement solely to the subcontractor’s supervisor: The site manager retains overall control of standards.

  2. Q22A crane lift is planned using a complex lifting arrangement. You discover that no temporary works design check has been completed. What action should you take?

    • APrevent the lift until the temporary works are properly designed and checked
    • BAllow the lift if the crane operator is competent
    • CProceed with the lift but restrict access around the area
    • DAsk the subcontractor to sign a risk acceptance form
    • ECarry out the lift at reduced load without redesign
    Show answer

    ✓ Correct answer: A. Prevent the lift until the temporary works are properly designed and checked

    Temporary works must be designed, checked, and implemented in accordance with legal duties under CDM and general health and safety law. Proceeding without a design check exposes workers to unacceptable risk. Why the other options are incorrect: • Allow the lift if the crane operator is competent: Competence does not replace the need for a proper temporary works process. • Proceed with the lift but restrict access around the area: Exclusion zones do not address the risk of structural failure. • Ask the subcontractor to sign a risk acceptance form: Risk acceptance forms do not override statutory duties. • Carry out the lift at reduced load without redesign: Reducing load does not eliminate the need for proper design approval.

  3. Q23A subcontractor questions why environmental controls are necessary for minor spills. How should you respond?

    • AExplain that environmental legislation requires prevention of pollution regardless of scale
    • BAgree that small spills are not legally significant
    • CAllow spills provided they are cleaned up later
    • DLeave environmental matters to specialist contractors
    • EApply controls only near watercourses
    Show answer

    ✓ Correct answer: A. Explain that environmental legislation requires prevention of pollution regardless of scale

    Environmental legislation aims to prevent pollution at source. Even small spills can cause harm and must be controlled. Why the other options are incorrect: • Agree that small spills are not legally significant: Legal duties apply regardless of perceived scale. • Allow spills provided they are cleaned up later: Delayed action may still result in pollution. • Leave environmental matters to specialist contractors: Site management retains responsibility for controls. • Apply controls only near watercourses: Environmental risk is not limited to watercourses.

  4. Q24A contractor asks whether they can start work before the construction phase plan has been finalised. What is the correct legal position?

    • AWork must not start until an adequate construction phase plan is in place
    • BWork can start if risks appear minimal
    • COnly high-risk activities need to wait
    • DWork may start with verbal agreement
    • EThe plan can be completed during the first week of work
    Show answer

    ✓ Correct answer: A. Work must not start until an adequate construction phase plan is in place

    Under CDM Regulations, a construction phase plan must be in place before work starts. This is a fundamental legal requirement. Why the other options are incorrect: • Work can start if risks appear minimal: Perceived low risk does not remove the legal requirement. • Only high-risk activities need to wait: The requirement applies to all construction work. • Work may start with verbal agreement: Verbal agreement does not meet statutory duties. • The plan can be completed during the first week of work: The plan must be completed prior to commencement.

  5. Q25You are planning works adjacent to a public footpath. What is your primary legal consideration?

    • AEnsuring risks to members of the public are eliminated or adequately controlled
    • BCompleting the work as quickly as possible to minimise exposure
    • CRelying on warning signage alone
    • DAssuming the local authority manages public safety
    • EOnly considering risks during working hours
    Show answer

    ✓ Correct answer: A. Ensuring risks to members of the public are eliminated or adequately controlled

    Health and safety legislation places a duty on duty holders to protect non-employees affected by the work. Public protection must be planned and implemented. Why the other options are incorrect: • Completing the work as quickly as possible to minimise exposure: Speed of work does not guarantee risk control. • Relying on warning signage alone: Signage alone is rarely sufficient protection. • Assuming the local authority manages public safety: The contractor retains responsibility for site-related risks. • Only considering risks during working hours: Risks may exist outside normal working hours.

  6. Q26You are reviewing subcontractor competence records and find expired training certificates. What is the correct course of action?

    • APrevent the individuals from carrying out the task until competence is confirmed
    • BAllow work to continue if experience is evident
    • CPermit work under additional supervision
    • DAccept certificates if renewal is booked
    • ELeave competence checks to the subcontractor
    Show answer

    ✓ Correct answer: A. Prevent the individuals from carrying out the task until competence is confirmed

    Those in control of construction work must ensure workers are competent. Allowing work without current evidence of competence breaches legal duties. Why the other options are incorrect: • Allow work to continue if experience is evident: Experience alone does not demonstrate current competence. • Permit work under additional supervision: Supervision does not remove the requirement for competence. • Accept certificates if renewal is booked: Booked renewal does not guarantee present competence. • Leave competence checks to the subcontractor: Responsibility for competence cannot be fully delegated.

  7. Q27You discover that a subcontractor has brought their own electrical equipment onto site without evidence of inspection or testing. What should you do to comply with legal duties?

    • APrevent the equipment being used until it has been checked and deemed safe
    • BAllow its use if no visible damage is present
    • CPermit use for short-duration tasks only
    • DAsk operatives to visually inspect the equipment themselves
    • ERecord the issue and review it during the next audit
    Show answer

    ✓ Correct answer: A. Prevent the equipment being used until it has been checked and deemed safe

    Electricity at Work Regulations require electrical equipment to be maintained in a safe condition. The manager must prevent use until suitable inspection and controls are confirmed. Why the other options are incorrect: • Allow its use if no visible damage is present: Absence of visible damage does not confirm electrical safety. • Permit use for short-duration tasks only: Duration of use does not reduce electrical risk. • Ask operatives to visually inspect the equipment themselves: Operatives are not responsible for formal inspection regimes. • Record the issue and review it during the next audit: Delaying action leaves workers exposed to immediate risk.

  8. Q28You are managing a project where licensed asbestos removal is required. The removal contractor arrives without evidence of notification to the enforcing authority. What is the correct managerial response?

    • AStop the work until confirmation of notification and compliance is provided
    • BAllow removal to proceed if the contractor is licensed
    • CProceed with removal outside normal working hours
    • DSupervise the work closely to reduce risk
    • EAllow removal of only small sections at a time
    Show answer

    ✓ Correct answer: A. Stop the work until confirmation of notification and compliance is provided

    The Control of Asbestos Regulations require licensed work to be notified to the enforcing authority. Allowing work to proceed without notification would be a breach of legislation and the manager must prevent this. Why the other options are incorrect: • Allow removal to proceed if the contractor is licensed: A licence alone does not remove the requirement for formal notification. • Proceed with removal outside normal working hours: Time of work does not affect legal notification requirements. • Supervise the work closely to reduce risk: Supervision cannot compensate for non-compliance with statutory requirements. • Allow removal of only small sections at a time: Phasing the work does not remove the need for notification.

  9. Q29You observe operatives manually handling heavy materials without mechanical aids, despite these being available on site. What is the correct managerial response?

    • AStop the activity and require suitable mechanical aids or revised controls to be used
    • BAllow the task to continue if operatives are comfortable
    • CReduce the load size and continue work
    • DPermit the task provided frequent breaks are taken
    • ELeave the decision to the subcontractor
    Show answer

    ✓ Correct answer: A. Stop the activity and require suitable mechanical aids or revised controls to be used

    The Manual Handling Operations Regulations require risks to be avoided or reduced so far as reasonably practicable. Where mechanical aids are available, they should be used. Why the other options are incorrect: • Allow the task to continue if operatives are comfortable: Comfort does not negate the risk of injury. • Reduce the load size and continue work: Reducing load size may still leave avoidable risk. • Permit the task provided frequent breaks are taken: Breaks do not remove the underlying hazard. • Leave the decision to the subcontractor: Overall responsibility for safe systems remains with site management.

  10. Q30You are informed that noise levels on site may exceed safe limits during planned works. What is the most appropriate action?

    • AAssess the noise risk and implement suitable controls before work starts
    • BProceed with work and issue ear protection only
    • CLimit exposure by shortening working hours
    • DRely on operatives to report hearing issues
    • EMonitor noise levels after the work is complete
    Show answer

    ✓ Correct answer: A. Assess the noise risk and implement suitable controls before work starts

    The Control of Noise at Work Regulations require risks from noise exposure to be assessed and controlled in advance. Controls must be planned before exposure occurs. Why the other options are incorrect: • Proceed with work and issue ear protection only: PPE alone may not sufficiently control exposure. • Limit exposure by shortening working hours: Shorter hours do not remove the need for assessment. • Rely on operatives to report hearing issues: Reactive reporting does not meet proactive legal duties. • Monitor noise levels after the work is complete: Controls must be in place before harm occurs.

Free practice here. Timed mocks when you are ready.

Use the free SMSTS Exam Prep 2026 sample, download the PDF, then unlock web-based timed mock exams for a full exam rehearsal.

Download PDFStart practice test