Q11A 'residual risk' is best described as:
✓ Correct answer: A. The risk that remains after controls have been applied
Residual risk is what remains after implementing control measures; it should be as low as reasonably practicable.
Topic: Hazard Identification & Risk Control
Q12Who is primarily responsible for identifying and managing hazards on a construction site?
✓ Correct answer: A. Everyone on site, including workers and management
WHS legislation places shared duties on all persons—workers, supervisors, and management.
Topic: Hazard Identification & Risk Control
Q13What does 'ALARP' stand for in WHS risk management?
✓ Correct answer: A. As Low As Reasonably Practicable
ALARP means risks must be reduced to a level as low as reasonably practicable given cost and practicality.
Topic: Hazard Identification & Risk Control
Q14Which of the following best describes a 'near miss'?
✓ Correct answer: A. An unplanned event that did not result in injury but had the potential to do so
Near misses are important warning signs and must be reported to prevent future incidents.
Topic: Hazard Identification & Risk Control
Q15When using a ladder, which risk is classified as a 'working at heights' hazard?
✓ Correct answer: A. Falling from the ladder
Falls from ladders are a working-at-heights hazard requiring appropriate controls.
Topic: Hazard Identification & Risk Control
Q16What is the purpose of a site safety induction?
✓ Correct answer: A. To inform workers about site-specific hazards, rules, and emergency procedures
Site inductions ensure every worker understands the hazards, controls, and emergency procedures specific to that site.
Topic: Hazard Identification & Risk Control
Q17A Risk Priority Number (RPN) combines which two factors?
✓ Correct answer: A. Likelihood of occurrence and severity of consequence
Risk is the product of likelihood and consequence (severity), used to prioritise controls.
Topic: Hazard Identification & Risk Control
Q18Which colour is universally used on construction sites to indicate 'danger – do not use'?
✓ Correct answer: A. Red
Red is the danger colour; red tags on equipment mean it is out of service and must not be used.
Topic: Hazard Identification & Risk Control
Q19What is the main purpose of a toolbox talk (safety meeting)?
✓ Correct answer: A. To brief workers on daily hazards and safe work practices before starting tasks
Toolbox talks keep hazard awareness high by reviewing daily risks and safe procedures before work begins.
Topic: Hazard Identification & Risk Control
Q20If you are unsure whether a task is safe to perform, you should:
✓ Correct answer: A. Stop work and seek clarification from a supervisor before proceeding
If in doubt, stop. WHS law gives workers the right to cease unsafe work until it is made safe.
Topic: Hazard Identification & Risk Control