HomeCSCS Card Test Prep UK 2026Questions 21–30
CSCS Card UKPart 3 of 3

CSCS Card UK Exam Questions & Answers 2026 (21–30)

CSCS Card UK practice questions and answers 2026. Tap an option to test yourself — you'll see the correct answer and a plain-English explanation for every question. Free, no login.

Practise CSCS Card UK questions free, download the PDF, or unlock timed mock exams when you are ready.
Download PDFWatch video
Multiple choice — pick the best answer, then reveal it
  1. Q21You are about to enter a confined space to carry out maintenance work. What must be in place BEFORE you enter, in addition to a risk assessment?

    • AA written permit-to-work system and a trained rescue team standing by
    • BWritten authorisation from the principal contractor and a designated fire warden
    • CA COSHH assessment completed within the previous 12 months
    • DA fluorescent jacket and a two-way radio issued by the site manager
    Show answer

    ✓ Correct answer: A. A written permit-to-work system and a trained rescue team standing by

    The Confined Spaces Regulations 1997 require a safe system of work that includes a permit-to-work, continuous atmospheric monitoring, and a pre-planned rescue arrangement before entry is made.

    Topic: CITB Health, Safety & Environment

  2. Q22An excavation on site is 1.8 metres deep. What is the minimum requirement to protect workers inside it from collapse?

    • APost a lookout at ground level to warn workers if the sides look unstable
    • BPlace spoil at least 0.5 metres from the edge; no other measures required
    • CEnsure the excavation is backfilled at the end of each working day
    • DSupport the sides with appropriate battering, benching, or proprietary shoring
    Show answer

    ✓ Correct answer: D. Support the sides with appropriate battering, benching, or proprietary shoring

    HSE guidance under HASAWA 1974 and CDM 2015 requires that excavations likely to collapse are made safe by battering the sides, installing proprietary trench supports, or other engineering measures before workers enter.

    Topic: CITB Health, Safety & Environment

  3. Q23Overhead power lines are present above a proposed construction access route. Which of the following control measures takes highest priority under the hierarchy of control?

    • AInstruct all plant operators to take extra care when passing underneath
    • BAttach goal-post barriers and height-restriction signs either side of the lines
    • CFit banksmen to guide vehicles under the lines one at a time
    • DReroute the access road so that plant never travels beneath the lines
    Show answer

    ✓ Correct answer: D. Reroute the access road so that plant never travels beneath the lines

    The hierarchy of control requires elimination first — rerouting the road removes the risk entirely, whereas goal-posts, banksmen, and driver instruction are lower-order controls that merely manage or reduce the hazard.

    Topic: CITB Health, Safety & Environment

  4. Q24A worker is using a class-three harness and fall-arrest lanyard attached to a single anchor point on a scaffold. The anchor point is level with the worker's waist. What is the PRIMARY additional hazard this arrangement creates compared with an anchor above the worker's head?

    • APUWER 1998 prohibits the use of lanyards attached below shoulder height
    • BThe lanyard will generate more static electricity in wet weather
    • CThe free-fall distance will be greater, increasing arrest forces on the body and risk of a swing-fall
    • DThe harness buckles may corrode faster when the anchor is at waist height
    Show answer

    ✓ Correct answer: C. The free-fall distance will be greater, increasing arrest forces on the body and risk of a swing-fall

    When an anchor is at waist level rather than above the head, the worker free-falls twice the lanyard length before arrest begins; longer free-fall increases arrest forces and the risk of a pendulum swing-fall striking a structure.

    Topic: CITB Health, Safety & Environment

  5. Q25Under the Confined Spaces Regulations 1997, who is legally permitted to carry out a rescue from a confined space where atmospheric monitoring has detected a dangerous gas level?

    • AThe permit-to-work issuer, provided they wear a disposable dust mask
    • BA pre-identified trained rescue team using appropriate equipment and a safe system of work
    • CAny trained worker on site who holds a valid CSCS card
    • DOnly emergency services who are already trained and equipped for the specific hazard
    Show answer

    ✓ Correct answer: B. A pre-identified trained rescue team using appropriate equipment and a safe system of work

    The Confined Spaces Regulations 1997 require that no rescue is attempted unless adequate rescue arrangements — including a trained team, correct personal protective and resuscitation equipment, and a safe method — are established before entry.

    Topic: CITB Health, Safety & Environment

  6. Q26A principal contractor receives a notification that an excavation on site has collapsed, burying a worker for three hours before rescue. The worker is taken to hospital with fractures. Under RIDDOR 2013, what reporting obligation applies?

    • AThe incident must be reported to the HSE as an over-seven-day injury within 15 days
    • BThe incident must be reported to the HSE immediately as a specified injury, and the site must preserve the scene
    • CThe incident is reportable only if the worker requires surgery, which triggers a 10-day reporting window
    • DNo report is required until the worker's GP confirms the injuries in writing
    Show answer

    ✓ Correct answer: B. The incident must be reported to the HSE immediately as a specified injury, and the site must preserve the scene

    RIDDOR 2013 classifies a fracture other than to a finger, thumb, or toe as a specified injury, which must be notified to the HSE without delay (immediately by phone or online), and the scene should be preserved pending investigation.

    Topic: CITB Health, Safety & Environment

  7. Q27During a risk assessment for working at height, the assessor concludes that neither avoidance nor collective fall-prevention measures are reasonably practicable. The next step in the Work at Height Regulations 2005 hierarchy is to minimise the consequences of a fall. Which combination of measures BEST achieves this?

    • APersonal fall-arrest equipment such as a harness with energy-absorbing lanyard, used with a correctly rated anchor, combined with a rescue plan
    • BRestricting work to periods of calm weather and ensuring all workers hold a current first-aid certificate
    • CA disposable coverall and bump cap to reduce abrasion injuries on impact
    • DIncreased supervision combined with a daily toolbox talk about fall risks
    Show answer

    ✓ Correct answer: A. Personal fall-arrest equipment such as a harness with energy-absorbing lanyard, used with a correctly rated anchor, combined with a rescue plan

    Where falls cannot be prevented, the Work at Height Regulations 2005 require fall-mitigation equipment — personal fall-arrest systems with certified anchors arrest the fall and limit injury, and a rescue plan addresses the risk of suspension trauma.

    Topic: CITB Health, Safety & Environment

  8. Q28What does the abbreviation COSHH stand for in UK health and safety law?

    • AControl of Substances Hazardous to Health
    • BControl of Site and Structural Hazards to Health
    • CConditions of Safe Substance Handling and Hygiene
    • DCompliance of Site Safety and Hazard Handling
    Show answer

    ✓ Correct answer: A. Control of Substances Hazardous to Health

    COSHH stands for the Control of Substances Hazardous to Health Regulations 2002, which require employers to assess and control workers' exposure to hazardous substances.

    Topic: CITB Health, Safety & Environment

  9. Q29Under the Manual Handling Operations Regulations 1992, what is the FIRST action an employer must take when a manual handling task cannot be avoided?

    • AIssue every worker with a back-support belt
    • BProvide manual handling training once a year
    • CAssess the risk of injury from the task
    • DLimit each lift to a maximum of 10 kg
    Show answer

    ✓ Correct answer: C. Assess the risk of injury from the task

    The Regulations require employers to carry out a suitable and sufficient risk assessment of any manual handling task that cannot be eliminated, before deciding on control measures.

    Topic: CITB Health, Safety & Environment

  10. Q30What colour are mandatory safety signs on a UK construction site, such as the sign requiring you to wear a hard hat?

    • AYellow with a black symbol
    • BRed with a white symbol
    • CBlue with a white symbol
    • DGreen with a white symbol
    Show answer

    ✓ Correct answer: C. Blue with a white symbol

    Under the Health and Safety (Safety Signs and Signals) Regulations 1996, mandatory signs — which instruct workers to take a specific action — are blue circles with a white symbol or text.

    Topic: CITB Health, Safety & Environment

Free practice here. Timed mocks when you are ready.

Use the free CSCS Card Test Prep UK 2026 sample, download the PDF, then unlock web-based timed mock exams for a full exam rehearsal.

Download PDFStart practice test