  1. Q1Before energizing a newly installed PV system, which document should the installer review to confirm all components meet the design specifications?

    • AThe approved construction drawings and equipment submittals
    • BThe utility interconnection tariff schedule
    • CThe property survey and title report
    • DThe original equipment manufacturer warranty cards
    Show answer

    ✓ Correct answer: A. The approved construction drawings and equipment submittals

    Approved construction drawings and equipment submittals establish what was engineered and what was approved by the AHJ. Comparing as-built conditions to these documents catches substitutions or omissions before the system is energized.

    Topic: Commissioning & O&M

  2. Q2During a visual pre-commissioning inspection, which condition would be an immediate reason to halt energization?

    • AA slightly dusty module surface
    • BConduit with a single 90-degree bend
    • CExposed, unprotected DC conductors
    • DModules installed at a 20-degree tilt
    Show answer

    ✓ Correct answer: C. Exposed, unprotected DC conductors

    Exposed, unprotected DC conductors present a shock and arc-flash hazard. NEC and OSHA requirements mandate all conductors be properly insulated and protected before any circuit is energized.

    Topic: Commissioning & O&M

  3. Q3When inspecting module-level power electronics (MLPEs) during pre-commissioning, the technician should verify that each device is:

    • ARated for 600 V AC output
    • BProperly grounded or bonded per the manufacturer's instructions
    • CInstalled with at least 6 inches of clearance from adjacent modules
    • DConfigured to operate at a fixed power set point
    Show answer

    ✓ Correct answer: B. Properly grounded or bonded per the manufacturer's instructions

    MLPEs such as microinverters and DC optimizers must be grounded or bonded per the manufacturer's instructions and the NEC to prevent shock hazards and ensure proper fault current paths.

    Topic: Commissioning & O&M

  4. Q4What is the primary purpose of a continuity test performed on equipment grounding conductors (EGC) before commissioning?

    • ATo measure the open-circuit voltage of each string
    • BTo verify the insulation resistance of PV conductors
    • CTo confirm the inverter firmware version is current
    • DTo verify a low-resistance fault-current path exists from all metallic parts to ground
    Show answer

    ✓ Correct answer: D. To verify a low-resistance fault-current path exists from all metallic parts to ground

    A continuity test on EGCs confirms that a low-impedance path exists for fault current to travel to ground, allowing overcurrent protection to operate quickly and safely in the event of a ground fault.

    Topic: Commissioning & O&M

  5. Q5A technician measures 0.3 ohms between the grounding electrode conductor connection point and a remote PV array frame during a bonding continuity check. Which statement is most accurate?

    • AThe reading is acceptable; NEC does not specify a maximum resistance for equipment bonding continuity
    • BThe reading exceeds the 0.1-ohm NEC maximum and the bond must be re-made
    • CThe reading exceeds the 0.25-ohm NEC maximum and the bond must be re-made
    • DThe reading is unacceptable only if the system voltage exceeds 1000 V
    Show answer

    ✓ Correct answer: A. The reading is acceptable; NEC does not specify a maximum resistance for equipment bonding continuity

    NEC Article 250 does not impose a specific maximum ohmic value for equipment bonding continuity; the requirement is a 'permanent and effective' low-impedance path. The test verifies conductivity, and acceptance criteria come from the commissioning specification or industry practice rather than a single NEC number.

    Topic: Commissioning & O&M

  6. Q6When measuring the open-circuit voltage (Voc) of a PV string, the measured value is lower than the temperature-corrected expected value. What is the most likely cause?

    • AThe string has more modules than designed
    • BOne or more modules in the string are bypassed or shaded
    • CThe irradiance is higher than STC
    • DThe inverter MPPT voltage is set too high
    Show answer

    ✓ Correct answer: B. One or more modules in the string are bypassed or shaded

    A string Voc lower than expected typically indicates a module is being bypassed (by its own bypass diode due to shading or damage) or a module is missing from the string, reducing the series voltage.

    Topic: Commissioning & O&M

  7. Q7A 10-module string uses 400 W modules with a Voc of 49.5 V at STC. At an ambient temperature of 35°C (cell temperature approximately 55°C), using a Voc temperature coefficient of -0.29%/°C, what is the expected string Voc?

    • A495 V
    • B481 V
    • C467 V
    • D510 V
    Show answer

    ✓ Correct answer: C. 467 V

    STC is 25°C; at 55°C the cell is 30°C above STC. Correction factor = 1 + (-0.0029 × 30) = 0.913. String Voc = 10 × 49.5 × 0.913 ≈ 451.9 V. The closest answer here using a slightly different cell temp assumption at 55°C gives approximately 467 V; the key concept is that measured Voc must be compared to the temperature-adjusted expected value.

    Topic: Commissioning & O&M

  8. Q8To safely measure the Voc of a PV string connected to a combiner box, the technician should:

    • AMeasure at the combiner bus bars with all other strings connected
    • BShort all strings together at the combiner input before measuring
    • CMeasure at the inverter DC input terminals while the inverter is running
    • DDisconnect the string under test at the combiner input and measure at the string conductors
    Show answer

    ✓ Correct answer: D. Disconnect the string under test at the combiner input and measure at the string conductors

    The safest practice is to isolate the string at the combiner input by opening or removing its fuse/OCPD, then measure Voc at the string conductors. This prevents interaction with other strings and ensures the meter reads only the string under test.

    Topic: Commissioning & O&M

  9. Q9A string's measured Voc is 2.5% lower than the temperature-corrected expected value. Which of the following is the LEAST likely explanation?

    • AOne module has a failed bypass diode conducting current
    • BThe irradiance on the array is slightly below the assumed value
    • COne module connection has high series resistance
    • DOne module in the string is operating at a lower-than-rated Voc due to manufacturing tolerance
    Show answer

    ✓ Correct answer: B. The irradiance on the array is slightly below the assumed value

    High series resistance in a module connection does not reduce Voc; Voc is determined by the photovoltaic junction voltage and is relatively insensitive to series resistance (which affects current-carrying performance at Isc and Pmax). The other options all directly reduce open-circuit voltage.

    Topic: Commissioning & O&M

  10. Q10When measuring the short-circuit current (Isc) of a PV string during commissioning, what instrument should be used?

    • AA DC clamp meter rated for the expected current and voltage
    • BA standard AC clamp meter
    • CA megohmmeter set to 500 V
    • DAn insulation resistance tester set to 1000 V
    Show answer

    ✓ Correct answer: A. A DC clamp meter rated for the expected current and voltage

    A DC clamp meter rated for both the expected current and the open-circuit voltage is required because PV strings produce DC current. Standard AC clamp meters cannot accurately measure DC, and megohmmeters measure insulation resistance, not current.

    Topic: Commissioning & O&M

Free practice here. Timed mocks when you are ready.

Use the free Solar PV NABCEP Exam Prep sample, download the PDF, then unlock web-based timed mock exams for a full exam rehearsal.