Solar PV NABCEP Exam Questions & Answers 2026 (21–30)

Solar PV NABCEP practice questions and answers 2026. Tap an option to test yourself — you'll see the correct answer and a plain-English explanation for every question. Free, no login.

Practise Solar PV NABCEP questions free, download the PDF, or unlock timed mock exams when you are ready.
Download PDFWatch video
Multiple choice — pick the best answer, then reveal it
  1. Q21A utility requires a 5-minute anti-islanding reconnect delay after a grid outage per IEEE 1547-2018. During commissioning, which test verifies this setting is correctly programmed in the inverter?

    • ASimulate a grid outage, restore grid power, and time the reconnect with a stopwatch
    • BApply a DC voltage ramp and measure the inverter's startup time
    • CMeasure the total harmonic distortion of the AC output
    • DPerform an insulation resistance test on the AC output conductors
    Show answer

    ✓ Correct answer: A. Simulate a grid outage, restore grid power, and time the reconnect with a stopwatch

    The reconnect delay is verified by simulating a grid outage (opening the AC disconnect), then restoring grid power and timing how long before the inverter resumes exporting. IEEE 1547-2018 default intentional delay is 300 seconds (5 minutes) for some abnormal conditions; the commissioning test must verify the programmed value matches the utility's requirement.

    Topic: Commissioning & O&M

  2. Q22Performance Ratio (PR) is defined as:

    • AActual energy produced divided by the nameplate DC power rating
    • BAC power output divided by DC power input to the inverter
    • CActual energy yield divided by the reference yield (energy the system would produce at STC with no losses)
    • DAnnual energy production divided by the system cost
    Show answer

    ✓ Correct answer: C. Actual energy yield divided by the reference yield (energy the system would produce at STC with no losses)

    PR = Actual yield / Reference yield. Reference yield is the energy the system would produce if every installed watt of STC capacity produced its rated output over the same period. PR captures all losses (temperature, wiring, inverter, soiling) in a single dimensionless metric.

    Topic: Commissioning & O&M

  3. Q23A newly commissioned 100 kWp PV system produces 1,200 kWh on its first clear day when the total in-plane irradiation is 6.5 kWh/m². What is the system's Performance Ratio for that day?

    • A0.72
    • B0.185 (this scenario is incomplete without irradiance area; the reference yield is 650 kWh for a 100 kWp system at 6.5 kWh/m²)
    • C1.85
    • D0.92
    Show answer

    ✓ Correct answer: B. 0.185 (this scenario is incomplete without irradiance area; the reference yield is 650 kWh for a 100 kWp system at 6.5 kWh/m²)

    Reference yield = STC power × irradiation / 1 kW/m² = 100 kW × 6.5 = 650 kWh. PR = 1200 / 650 ≈ 1.85. A PR > 1 is physically impossible and indicates either an irradiance sensor error, an incorrectly stated STC capacity, or a measurement error—this would trigger investigation during commissioning.

    Topic: Commissioning & O&M

  4. Q24A newly commissioned utility-scale PV plant achieves a first-year PR of 0.76. A well-functioning crystalline silicon system in a hot climate typically achieves a PR in which range?

    • A0.55–0.65
    • B0.90–0.95
    • C0.65–0.70
    • D0.75–0.85
    Show answer

    ✓ Correct answer: D. 0.75–0.85

    For crystalline silicon PV in a hot climate, a PR of 0.75–0.85 is typical, accounting for temperature losses, soiling, wiring losses, and inverter efficiency. Values below 0.70 often indicate a significant fault; values above 0.85 in hot climates are exceptional.

    Topic: Commissioning & O&M

  5. Q25During commissioning acceptance testing, the measured PR is 0.68 against a guaranteed PR of 0.78. Before declaring a performance failure, the engineer should first:

    • AApply temperature correction to the measured PR because high cell temperatures artificially depress PR
    • BRequest a refund from the contractor since the guarantee has been missed
    • CIncrease the array tilt to improve irradiance capture
    • DReplace underperforming modules with higher-wattage modules
    Show answer

    ✓ Correct answer: A. Apply temperature correction to the measured PR because high cell temperatures artificially depress PR

    Raw PR is temperature-dependent; hot days depress apparent PR. Applying a cell-temperature correction (per IEC 61724) normalizes PR to a reference temperature, giving a fair comparison to the guarantee value. If the temperature-corrected PR still misses the guarantee, then further investigation is warranted.

    Topic: Commissioning & O&M

  6. Q26Which sensor is essential in a PV monitoring system to calculate the system's Performance Ratio?

    • AWind speed anemometer
    • BPyranometer or irradiance reference cell
    • CAmbient humidity sensor
    • DGrid voltage transducer
    Show answer

    ✓ Correct answer: B. Pyranometer or irradiance reference cell

    PR requires knowledge of the in-plane irradiance. A pyranometer or calibrated reference cell mounted at the array tilt provides the irradiance data needed to calculate reference yield for the PR calculation.

    Topic: Commissioning & O&M

  7. Q27What data logging interval is commonly recommended by IEC 61724 for PV system performance monitoring?

    • A1-second intervals
    • B30-minute intervals
    • CDaily totals only
    • D1-minute or 15-minute intervals
    Show answer

    ✓ Correct answer: D. 1-minute or 15-minute intervals

    IEC 61724-1 recommends a data logging interval of 1 minute for high-resolution monitoring or up to 15 minutes for standard monitoring. This captures transient shading and fault events that daily totals would obscure.

    Topic: Commissioning & O&M

  8. Q28A monitoring system consistently shows lower energy production from strings on the east side of the roof during afternoon hours. The most likely explanation is:

    • AThe east-side modules have a higher Voc temperature coefficient
    • BThe monitoring gateway has a communication error on the east-side channel
    • CThe east-facing strings experience afternoon shading from roof penetrations or nearby objects
    • DThe east-side strings are wired in reverse polarity
    Show answer

    ✓ Correct answer: C. The east-facing strings experience afternoon shading from roof penetrations or nearby objects

    East-facing or east-side strings receive maximum irradiance in the morning and experience shading or reduced irradiance in the afternoon as the sun moves west. Consistent afternoon underperformance from a specific location is a classic shading signature.

    Topic: Commissioning & O&M

  9. Q29A monitoring system shows inverter AC power output that is consistently 3% higher than what the string-level DC power sum indicates. This discrepancy most likely points to:

    • AA calibration offset or scaling error in the DC current sensors
    • BThe inverter operating at greater than 100% efficiency
    • CThe AC power meter reading reactive power instead of real power
    • DSoiling on the DC-side irradiance sensor
    Show answer

    ✓ Correct answer: A. A calibration offset or scaling error in the DC current sensors

    Inverters cannot produce more AC power than DC power input (efficiency ≤ 100%). A consistent positive discrepancy where AC > DC sum almost always indicates a calibration or scaling error in the DC current transducers or power calculation, not a physical efficiency violation.

    Topic: Commissioning & O&M

  10. Q30Before a utility will grant Permission to Operate (PTO) for a grid-tied PV system, they typically require:

    • AA signed letter from the system owner
    • BAn infrared scan of all modules
    • CA signed interconnection agreement and passing final inspection
    • DProof of homeowner's insurance
    Show answer

    ✓ Correct answer: C. A signed interconnection agreement and passing final inspection

    PTO requires that the utility's interconnection agreement be executed and that the system has passed a final inspection by the AHJ. These steps confirm the system meets safety and technical requirements before the utility authorizes operation.

    Topic: Commissioning & O&M

Free practice here. Timed mocks when you are ready.

Use the free Solar PV NABCEP Exam Prep sample, download the PDF, then unlock web-based timed mock exams for a full exam rehearsal.