HomeSolar PV NABCEP Exam PrepQuestions 11–20
Solar PV NABCEPPart 2 of 3

Solar PV NABCEP Exam Questions & Answers 2026 (11–20)

Solar PV NABCEP practice questions and answers 2026. Tap an option to test yourself — you'll see the correct answer and a plain-English explanation for every question. Free, no login.

Practise Solar PV NABCEP questions free, download the PDF, or unlock timed mock exams when you are ready.
Download PDFWatch video
Multiple choice — pick the best answer, then reveal it
  1. Q11The measured Isc for a string is 10% above the nameplate Isc at STC. The irradiance is measured at 950 W/m². What is the most accurate interpretation?

    • AThe string has a shorted bypass diode increasing current
    • BThe measurement confirms correct wiring; 10% above is acceptable
    • CIrradiance alone cannot explain the discrepancy; further investigation is needed
    • DThe modules are underperforming because STC specifies 1000 W/m²
    Show answer

    ✓ Correct answer: C. Irradiance alone cannot explain the discrepancy; further investigation is needed

    At 950 W/m² the expected Isc would be about 95% of nameplate STC Isc. A measured value 10% above STC nameplate at lower irradiance (meaning roughly 15–16% above what is expected) is anomalous and warrants investigation for wiring errors such as mis-connected parallel strings.

    Topic: Commissioning & O&M

  2. Q12A technician clamp-meters a combiner box output and reads an Isc that is exactly 3× the per-string Isc at the same irradiance, but the combiner is designed for 4 strings. What does this indicate?

    • ANormal operation; three of four strings are producing rated current
    • BThe fourth string is reverse biased and reducing total current
    • CThe combiner has a 3:1 step-up ratio built in
    • DOne string is not contributing current, likely due to an open circuit or blown fuse
    Show answer

    ✓ Correct answer: D. One string is not contributing current, likely due to an open circuit or blown fuse

    At the combiner output, total current equals the sum of all parallel string currents. If the measured total equals 3× per-string Isc instead of 4×, one string is contributing zero current—most likely an open fuse, disconnect, or broken conductor in that string.

    Topic: Commissioning & O&M

  3. Q13What instrument is used to perform an insulation resistance test on PV wiring?

    • ADigital multimeter set to continuity
    • BMegohmmeter (megger)
    • CClamp-on ammeter
    • DPower quality analyzer
    Show answer

    ✓ Correct answer: B. Megohmmeter (megger)

    A megohmmeter applies a high DC test voltage (typically 500–1000 V for PV systems) and measures the resulting leakage current to calculate insulation resistance in megohms, which a standard multimeter cannot do.

    Topic: Commissioning & O&M

  4. Q14Before performing an insulation resistance test on PV array conductors, the technician should:

    • ADisconnect the inverter and all loads, and short the positive and negative conductors together at the array end
    • BLeave the inverter connected to provide a reference ground
    • CEnergize the array and test under live conditions
    • DRemove all modules from the array to isolate the conductors
    Show answer

    ✓ Correct answer: A. Disconnect the inverter and all loads, and short the positive and negative conductors together at the array end

    Shorting the positive and negative together at the array end and disconnecting the inverter allows the megohmmeter to test all conductor insulation simultaneously against ground from a single measurement point without back-feeding voltage into the inverter.

    Topic: Commissioning & O&M

  5. Q15IEC 62446-1 recommends a minimum insulation resistance value for PV strings. Which value is typically cited as the minimum acceptable for a system under 1 kVdc?

    • A0.1 MΩ
    • B0.5 MΩ
    • C1 MΩ
    • D10 MΩ
    Show answer

    ✓ Correct answer: C. 1 MΩ

    IEC 62446-1 specifies a minimum insulation resistance of 1 MΩ for systems with a maximum system voltage ≤1000 Vdc. Values below this indicate degraded insulation that could lead to ground faults or leakage currents.

    Topic: Commissioning & O&M

  6. Q16A technician tests a 1000 V string and obtains 0.6 MΩ insulation resistance. After drying out wet conduit and retesting, the value rises to 4.8 MΩ. Which statement best describes the situation?

    • ABoth readings fail IEC 62446-1; the array should be decommissioned
    • BThe first reading is acceptable because moisture is temporary
    • CThe second reading fails; values above 2 MΩ indicate a different fault
    • DThe first reading failed the 1 MΩ minimum; the second passes, and moisture was the root cause
    Show answer

    ✓ Correct answer: D. The first reading failed the 1 MΩ minimum; the second passes, and moisture was the root cause

    IEC 62446-1 requires ≥1 MΩ for systems ≤1000 V. The initial 0.6 MΩ reading failed that threshold. After drying, the 4.8 MΩ value clears the minimum, confirming moisture in the conduit was temporarily compromising insulation resistance.

    Topic: Commissioning & O&M

  7. Q17During grid-tied inverter commissioning, the inverter performs an automatic anti-islanding check. What is the purpose of this check?

    • ATo ensure the inverter will shut down when utility grid power is lost
    • BTo verify the inverter MPPT algorithm is functioning correctly
    • CTo measure the DC input impedance of the PV array
    • DTo calibrate the inverter's revenue-grade power meter
    Show answer

    ✓ Correct answer: A. To ensure the inverter will shut down when utility grid power is lost

    Anti-islanding protection ensures the inverter disconnects from the grid when utility power is lost, preventing the inverter from energizing a de-energized utility line and protecting utility workers performing maintenance.

    Topic: Commissioning & O&M

  8. Q18The correct sequence for starting up a string inverter from a completely de-energized state is:

    • AClose AC disconnect → close DC disconnect → enable inverter
    • BEnable inverter → close DC disconnect → close AC disconnect
    • CClose DC disconnect → enable inverter → close AC disconnect
    • DClose AC disconnect → close DC disconnect → allow inverter to self-start
    Show answer

    ✓ Correct answer: D. Close AC disconnect → close DC disconnect → allow inverter to self-start

    The AC disconnect is closed first to establish the grid reference the inverter needs. Then the DC disconnect is closed to provide PV power. The inverter then performs its internal checks (grid voltage/frequency, anti-islanding delay) and self-starts without a separate manual enable step.

    Topic: Commissioning & O&M

  9. Q19An inverter displays a 'Grid Frequency Out of Range' fault on first startup. The grid voltage and waveform look normal on an oscilloscope. What should the technician check first?

    • AThe DC input voltage from the PV array
    • BThe inverter's programmed grid frequency setting
    • CThe insulation resistance of the AC output conductors
    • DThe firmware version of the monitoring gateway
    Show answer

    ✓ Correct answer: B. The inverter's programmed grid frequency setting

    Grid-tied inverters have configurable frequency windows. If the inverter was configured for 50 Hz (e.g., exported from a European market) but the grid is 60 Hz, the inverter will fault. Checking and correcting the programmed frequency setting resolves this.

    Topic: Commissioning & O&M

  10. Q20After initial startup, a three-phase inverter shows power output on two phases but not the third. What is the most likely cause?

    • AThe inverter's MPPT range excludes the current PV voltage
    • BThe DC combiner has a blown string fuse
    • CA loose or open connection on the third AC output conductor
    • DThe revenue meter is configured for single-phase measurement
    Show answer

    ✓ Correct answer: C. A loose or open connection on the third AC output conductor

    An open connection on one AC phase will prevent current flow on that phase only, while the other two phases operate normally. A DC-side issue would typically affect all phases equally.

    Topic: Commissioning & O&M

Free practice here. Timed mocks when you are ready.

Use the free Solar PV NABCEP Exam Prep sample, download the PDF, then unlock web-based timed mock exams for a full exam rehearsal.

Download PDFStart practice test